Cam Hoa Solar Power plant
In the afternoon of June 4, under the witness of the Vice Chairman of the Provincial People's Committee Duong Tat Thang, the Council accepted the Hoanh Son Group Joint Stock Company (the investor) and the technical contractor energized the 110KV substation. Cam Hoa solar power plant (Cam Xuyen - Ha Tinh) was successful
|
Assignment name:
Cam Hoa Solar Power plant
|
Approx. value of the Contract:
48.000 USD
|
Country: Viet Nam
Location within country: Cam Xuyen district, Ha Tinh province
|
Duration of assignment (month): 30 days
|
Name of Client:
Ha Tinh solar power JSC
Name and email of the contact: …………….
|
Total No. of man-months of the assignment:
|
Address of Client:
No. 116 Tran Phu st., Tran Phu ward, Ha Tinh city
|
Approx. value of the services provided by our firm under the contract: 48.000 USD
|
Start date (month/year): 16/12/2018
Completion date (month/year): 16/01/2019
|
|
Narrative description of project:
- 50.0MW capacity, located on an area of 65ha;
- Fixed photovoltaic module, polycrystalline cell, 20 Inverter;
- 110kV substation;
- 110kV transmission line 15.4km long.
|
Description of actual services provided by our staff within the assignment:
- Technical Design, Detailed drawing design for 22/110kV booster station, 110kV transmission line.
|
|